Guidelines For Effective Railway Joint Installation

Mar 11, 2024 Leave a message

Rail Joint Installation Procedures

The railway joints have 4 or 6 holes on their body. Before installation, rail screws should be installed with spring washers, and lubricating oil should be applied to the surface of rail screws and spring washers.

During the installation of railway joints, insert the railway joint gasket at the joint to ensure conformity to the standard and adjust the central position of steel rails simultaneously. Straighten the outer rail stock according to the position of the center pile.

It's important to note that the length of each pair of steel rail lengths may have errors, with positive and negative offsets at times.

Rail Joint

Notes on the Railway Joint Installation Process

  • Oil the lifting parts of railway joints, steel rails, and rail bolts.
  • When threading the railway joint screws, stagger the positions of the screw caps internally and externally.
  • In the case of a four-hole railway joint, first tighten the middle two bolts and then move on to both sides. After tightening the screws on the sides, revisit the middle two.
  • When screwing the rail bolts, use a 55cm screw wrench handle as the standard. Avoid using excessively long screw wrenches or wrenches for two persons.
  • If the rail bolt cannot be threaded, lightly hammer both ends of the railway joint, aiming at the eyes of the railway joints. It's not necessary to excessively tighten the rail screw bolts.
  • When wrenching the track bolts, ensure the spring washer opening is facing downward.